OVERALL HOUSE
ROOF
PHASE 2: POA FOR ROOF REDO
DEMO
POA FOR BASEMENT CHIMNEY/LOLLY COLUMNS – NEEDS TO HAPPEN BEFORE WE LAY FLOOR IN FRONT ROOMS & APPLY FINISHES
HVAC
MAKE A DECISION ON NATURAL GAS V. CONTINUING WITH OIL FURNACE
O IF OIL: INSTALL POWER VENT, SERVICE FURNACE, PICK OIL COMPANY
O IF NATURAL GAS: SCHEDULE CONVERSION
PLUMBING
INSULATE PIPES IN THE CRAWLSPACE
FLOORING
REMOVE FLOORING THROUGHOUT
PATCH FLOORING
INSTALL SUBFLOOR
INSTALL HARDWOOD IN KICTHEN, NOOK, FRONT ROOM (EXPECTED DELIVERY: NOVEMBER)
PAINT MUDROOM FLOOR
OTHER
SWITCH OUT KNOBS ON ALL DOORS
PAINT MUDROOM WALLS, CABINETS
KITCHEN & NOOK
DEMO
DEMO BACKSPLASH
FINAL BITS & PIECES OF DEMO
ELECTRICALS
FINISH RUNNING WIRES SO CAITLIN CAN INSULATE
WIRE FOR PHONE
INSTALL FAN ELECTRICAL BOX
INSTALL NOOK PENDANT (CAN WE DO BEFORE PLASTER?)
INSTALL KITCHEN FAN
INSTALL PHONE, SET UP VERIZON VM
INSTALL POT LAMP SURROUNDS
FRAMING
FILL IN BLOCKS, AND STRAPPING
SCREW IN BOLTS FOR SUPPORT
INSULATION
SEAL UP CRAWL SPACE OVER BATHROOM AFTER FAN IS INSTALLED
STUFF BATTING WHERE WE CAN IN VAULTED CEILING
INSULATE KICTHEN WALLS
APPLY FOIL INSULATION TO KITCHEN CEILING
PLUMBING
MAKE A DECISION ON VENT OVER STOVE (NEED TO DRAW OUT)
WALLS & CEILINGS
HANG CEILIING SHEETROCK IN NOOK
HANG WALL SHEETROCK IN NOOK
HANG CEILING SHEETROCK IN KITCHEN
HANG WALL SHEETROCK IN NOOK
FIND HIRED HELP FOR PLASTER COAT
PLASTER KITCHEN & NOOK
PAINT
CONSTRUCTION
MAKE A DECISION RE: STAIR LANDING AREA (HUNG CABINET, COUNTER, WINDOW, RADIATOR…)
NEW DOOR FOR BASEMENT, HARDWARE, ETC
FINISH WORK
FRAME IN WINDOWS, ALL TRIMWORK
PAINT TRIMWORK
OTHER
RECYCLE BIN FOR UNDER SINK
PAINT ALL BUILT-IN CABINETS
UPHOLSTER NOOK BENCH
PHASE 2: COUNTER TOP PLAN
SECURE MARBLE TOP ON ISLAND
SCRUB DOWN ALL APPLIANCES
SCRUB DOWN ALL WINDOWS, BEGIN CONSIDERING TREATMENTS
FRONT ROOM
DEMO
WALLS
CORNER UNIT BUILT-IN
ELECTRICALS
WIRE FOR CANDLABRA WITH DIMMER ON DINING ROOM SIDE
WIRE FOR SIDE TABLE LAMPS (UNDER COUCH ON FLOOR)
WIRE FOR ENTERTAINMENT SYSTEM (INCLUDING CABLE, ETC)
FRAMING
ADD POSTS IN FRONT ROOM, HARDWARE
PATCH BEAM IN FRONT ROOM
INSULATION
APPLY FOIL INSULATION TO CEILING?
FILL IN WALL HOLES WITH GREAT STUFF?
INSULATE FRONT ROOM WALLS
WALLS & CEILINGS
HANG SHEETROCK – WALLS AND CEILING (BETWEEN BEAMS)
HIRED HELP FOR PLASTER COAT
PLASTER FRONT ROOM
PAINT
HVAC
NEW ZERO-CLEARANCE GAS FIREPLACE
CONSTRUCTION
ENTERTAINMENT BUILT IN USING SAVAGED FIREPLACE
WALL OF BOOKS ON DININGROOM SIDE
FINISH WORK
FRAME IN WINDOWS, ALL TRIMWORK
PAINT TRIMWORK
OTHER
SCRUB DOWN ALL WINDOWS, BEGIN CONSIDERING TREATMENTS
BATHROOM
ELECTRICALS
FIX BATHROOM CIRCUITRY
WALLS & CEILINGS
PATCH
REPAINT
OTHER
VENT BATHROOM FAN OUT ROOF
FIX DRYER VENT
INSTALL MEDICINE CABINET
REMOVE SHELVES?
BRING IN WHITE CABINET FOR ADDITIONAL STORAGE
YARD/EXTERIOR
MOW LAWN/WEEDWACK/WEED
RECONFIRGURE ENTRY WITH EXPANDED LANDING & DECK
NEW BACK DOOR
NEW MAILBOX
REMOVE GRAPEVINES
REMOVE RED CEDAR AND PINE TREE
ROTATIL BACKYARD, PLANT GRASS SEED
SOMETHING TO HOLD UP BEE BALM & FLOCKS